A $6.6 millionTreatment
Plant expansion project is currently underway and consists of the
following:
- Primary Pumps - Increase
capacity of existing pumps and add two submersible pumps
- Influent Screening
- provide a third screen
- Grit Removal - add
a third grit removal unit
- Intermediate Pumps
- increase the capacity of each existing pump and add one submersible
pump
- Clarifiers - install
a fourth clarifier
- Filters - add two
filters
- Effluent Disinfection
- add a third contact tank
- Sludge Disposal -
add a composting operation which will provide a product useful
by the Utility, the City of Jacksonville, and possible, private
individuals for landscaping and as a soil conditioner.
- Repair Items - recoat
an repaint metals, revise area lighting, concrete repairs, resurface
roads, rotor replacement, sludge pump replacement, clarifier density
baffles, replenish filter media, new return sludge controls, miscellaneous
piping modifications, chlorine building modifications, recycle
pump station replacements.
|